Project Detail
Project Main Menu

Project Overview
Project Name: ESD: SWM 99
Project Type: Water Quality Retrofit
Project Description: Convert to Level 1 Constructed Wetland in order to improve treatment efficiency and therefore improve water quality.
Project Manager: Benjamin A. Eib     send an email
Alternate Manager: Tony Marquez     
Agency Name: Public Works QPR?: Yes
Magisterial District: Gainesville
Original Budget: $50,000.00

Revised Budget:

$96,458.64
Original Start Date: 4/21/2014

Revised Start Date:

Original End Date: 8/18/2014

Revised End Date:

11/1/2015
Last Updated On: 2/19/2016 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Bull Run Watershed OCA

$50,000.00 $96,458.64 4/1/2014
       
Total Amount: $50,000.00 $96,458.64



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Design/Permitting 4/21/2014 11/24/2014 5/23/2014 5/15/2015 ES  
2. Construction 7/8/2014 2/1/2015 8/18/2014 7/15/2015 CSB  
3. Asbuilt 7/15/2015 10/1/2015 10/16/2015 CSB  
4. Planting 10/15/2015 10/31/2015 Contractor  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue