Project Detail
Project Main Menu

Project Overview
Project Name: SW: Landfill Liner Design and Construction of Phase II, Cell C
Project Type: Landfill CIP Project
Project Description: The project includes all work necessary to design and construct the Phase II, Cell C lined landfill cell.
Project Manager: Sadhu S. Sandhu     send an email
Alternate Manager: Thomas J. Smith     
Agency Name: Public Works QPR?: Yes
Magisterial District: Coles
Original Budget: $6,007,800.00

Revised Budget:

$7,050,518.00
Original Start Date: 9/1/2013

Revised Start Date:

Original End Date: 12/31/2014

Revised End Date:

10/15/2015
Last Updated On: 6/25/2020 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Solid Waste Fees and Capital Reserve

$6,007,800.00 $7,050,518.00 7/1/2013
       
Total Amount: $6,007,800.00 $7,050,518.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design 9/1/2013 2/28/2014    
2. Invitation for Bid 2/18/2014 4/15/2014    
3. Construction 5/15/2014 12/31/2014 10/15/2015    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue