Project Detail
Project Main Menu

Project Overview
Project Name: Old Linton Hall Rd Landscaping Buffer
Project Type: Landscaping
Project Description: The project will consists of the installation of 25 shade trees on the southbound side the road along Old Linton Hall Rd in between Wellington Rd and Huron Drive.
Project Manager: Ed W. Wheeling     send an email
Alternate Manager: Michelle M. Morris     
Agency Name: Neighborhood Services QPR?: Yes
Magisterial District: Gainesville
Original Budget: $23,000.00

Revised Budget:

$23,000.00
Original Start Date: 1/1/2014

Revised Start Date:

Original End Date: 5/31/2014

Revised End Date:

Last Updated On: 6/5/2014 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Gainesville district has allocated funds to cover the cost of installation and five years of maintenance. OCA 415898.

$23,000.00 --- 1/1/2014
       
Total Amount: $23,000.00 $23,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. The County has received Land Use Permit approval from VDOT. 4/1/2014 5/31/2014 1  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue