Project Detail
Project Main Menu

Project Overview
Project Name: ESD: Powells Creek 725 Phase 1 Stream Restoration
Project Type: Stream Restoration
Project Description: Construct restoration along 3,100 linear feet of Powells Creek. Phase 1 of a five phase project.
Project Manager: Thomas E. Dombrowski     send an email
Alternate Manager: Benjamin A. Eib     
Agency Name: Public Works QPR?: Yes
Magisterial District: Potomac
Original Budget: $1,330,000.00

Revised Budget:

$1,330,000.00
Original Start Date: 12/31/2014

Revised Start Date:

Original End Date: 1/31/2017

Revised End Date:

12/31/2017
Last Updated On: 6/20/2016 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Powell's Creek CIP

$665,000.00 --- 12/31/2014

2. SLAF Matching Grant

$665,000.00 ---
       
Total Amount: $1,330,000.00 $1,330,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Topographic and Photogrametric Survey 2/15/2015 6/15/2015 TED  
2. GEOMORPHIC STUDY 1/15/2015 6/15/2015 TED  
3. Hydrologic Study 4/15/2015 6/15/2015 6/15/2016 TED  
4. HYDRAULIC STUDY 4/15/2015 6/15/2015 6/15/2016 TED  
5. CONCEPT DESIGN DEVELOPMENT OF PHASE 1 PROJECT AREA 12/31/2014 1/31/2016 7/15/2016 TED  
6. Final Design 7/1/2016 12/31/2016 PB  
7. Construction 7/1/2017 12/31/2017 TBD  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue