Project Detail
Project Main Menu

Project Overview
Project Name: PW: Powells Creek 725 Phase 1 Stream Restoration
Project Type: Stream Restoration
Project Description: Construct restoration along 3,100 linear feet of Powells Creek. Phase 1 of a five phase project. Project design is completed. 100 percent design has been received and submitted for review.Need to prepare FEMA application. Water Quality permit from USCOE is secured on 6/2/20.FEMA COLMAR has been approved (9/15/2021). Trees have been planted in the floodplain and will be completed by July 2022.
Project Manager: Thomas E. Dombrowski     send an email
Alternate Manager: Benjamin A. Eib     
Agency Name: Public Works QPR?: Yes
Magisterial District: Potomac
Original Budget: $5,585,298.59

Revised Budget:

$5,585,298.59
Original Start Date: 12/31/2014

Revised Start Date:

Original End Date: 1/31/2017

Revised End Date:

10/31/2022
Last Updated On: 11/10/2022 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. SLAF Matching Grant

$665,000.00 ---

2. DEQ Stormwater Local Assistance Fund (SLAF) #17-22

$162,500.00 ---

3. County Watersheds CIP

$4,757,798.59 ---
       
Total Amount: $5,585,298.59 $5,585,298.59



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Hydrologic Study 4/15/2015 6/15/2015 6/15/2016 TED  
2. HYDRAULIC STUDY FEMA FLOODPLAIN SUBMITTAL 4/15/2015 6/15/2015 6/15/2019 TED  
3. Construction 7/1/2017 7/15/2019 1/15/2019 10/31/2022 TED  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue