Project Detail
Project Main Menu

Project Overview
Project Name: ESD: 1948 Richmond Avenue
Project Type: Drainage Improvement
Project Description: Project includes installation of new storm drainage system and grading of swale to address flooding complaints.
Project Manager: Juan P. Alfaro     send an email
Alternate Manager: Tony Marquez     
Agency Name: Public Works - Environmental Services QPR?: Yes
Magisterial District: Woodbridge
Original Budget: $30,000.00

Revised Budget:

$41,764.50
Original Start Date: 8/1/2014

Revised Start Date:

Original End Date: 2/27/2015

Revised End Date:

6/1/2015
Last Updated On: 6/5/2015 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Marumsco Creek Watershed

$30,000.00 $41,764.50 2/28/2015
       
Total Amount: $30,000.00 $41,764.50



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Topographic Survey 8/11/2014 9/10/2014 RN  
2. Design 9/11/2014 10/15/2014 AM  
3. Construction 12/3/2014 1/2/2015 CS  
4. Plat Recordation 1/5/2015 2/27/2015 6/1/2015 JA  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue