Project Name: FCM: Adult Detention Center Phase II
Project Type: New Construction
Project Description: This project provides a 204 bed expansion adjacent to the existing detention center and some renovations to the main jail. The addition will provide bed space for future inmate population growth.
Project Manager: David R. Scott     send an email
Alternate Manager: John W. Mitchell     
Agency Name: Facilities Construction Management QPR?: Yes
Magisterial District: Woodbridge
Original Budget: $45,723,451.00

Revised Budget:

$45,723,451.00
Original Start Date: 4/25/2015

Revised Start Date:

4/25/2015
Original End Date: 9/30/2019

Revised End Date:

9/30/2019
Last Updated On: 10/3/2016 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. General Fund

$45,723,451.00 --- 4/21/2015
       
Total Amount: $45,723,451.00 $45,723,451.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design Phase 4/27/2015 8/31/2016 11/15/2016    
2. Building Permit Phase 9/1/2016 11/15/2016 1/1/2017 2/15/2017    
3. Advertise and Award Phase 1/1/2017 2/16/2017 4/1/2017 6/30/2017    
4. Construction Phase 4/1/2017 7/1/2017 7/1/2019 9/30/2019    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
9/27/2107The site plan was submitted on August 12th for an initial quality control check. Corrections were made and the site plan was resubmitted on September 21, 2016.
9/27/2106An early assistance meeting is scheduled with the Building Code Officials and Fire Marshal Office on October 12, 2016. The 95% Construction Documents will be revised per the outcome of the meeting and submitted to the County by the end of October 2016.
9/27/2016Facilities Construction Management (FCM) and the architect-engineer (HOK) plan to submit the 100% Construction Documents to the Building Code Officials on November 15, 2016. This is contingent upon inputs received at the early assistance meeting on October 12, 2016.

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue