Project Name: FCM: Adult Detention Center Phase II
Project Type: New Construction
Project Description: This project provides a 204 bed expansion adjacent to the existing detention center and some renovations to the main jail. The addition will provide bed space for future inmate population growth.
Project Manager: Karen L. FitzGibbon     send an email
Alternate Manager: LouAnn D. Purkins     
Agency Name: Facilities Construction Management QPR?: Yes
Magisterial District: Woodbridge
Original Budget: $45,723,451.00

Revised Budget:

$45,723,451.00
Original Start Date: 4/25/2015

Revised Start Date:

4/25/2015
Original End Date: 9/30/2019

Revised End Date:

3/30/2020
Last Updated On: 6/15/2018 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. General Fund

$45,723,451.00 --- 4/21/2015
       
Total Amount: $45,723,451.00 $45,723,451.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design Phase 4/27/2015 8/31/2016 12/8/2016    
2. Building Permit Phase 9/1/2016 12/9/2016 1/1/2017 5/15/2017    
3. Advertise and Award Phase 1/1/2017 5/16/2017 4/1/2017 8/2/2017    
4. Construction Phase 4/1/2017 12/4/2017 8/2/2019 3/30/2020    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue