Project Name: SW: Landfill Cap Design and Construction of Phase II, Sequence Four
Project Type: Landfill CIP Project
Project Description: The project includes all work necessary to design and construct a final closure cap for Phase II, Sequence 4
Project Manager: Sadhu S. Sandhu     send an email
Alternate Manager: Thomas J. Smith     
Agency Name: Public Works QPR?: Yes
Magisterial District: Coles
Original Budget: $3,638,075.00

Revised Budget:

$3,638,075.00
Original Start Date: 8/1/2017

Revised Start Date:

Original End Date: 11/30/2018

Revised End Date:

1/30/2019
Last Updated On: 1/8/2020 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Solid Waste Fees/Closure Account

$3,638,075.00 --- 7/1/2017
       
Total Amount: $3,638,075.00 $3,638,075.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design 8/1/2017 1/31/2018    
2. Invitation for Bid (Neogotiate Contract) 12/1/2017 3/31/2018    
3. Construction 4/1/2018 11/30/2018 1/16/2019    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue
8/15/2017Cap installation is required by State and Federal regulations within 180 days after the final elevation is achieved.

2. Schedule/Timing Issues     

 

Date

Issue
7/8/2019The project is complete in its entirety and the contract has been finally closed. On June 6, 2019, the County received partial closure certification approval letter from DEQ. The final payment including retainage has been paid during FY2019.

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue