Project Detail
Project Main Menu

Project Overview
Project Name: SW: Landfill Cap Design and Construction of Phase II, Sequence Four
Project Type: Landfill CIP Project
Project Description: The project includes all work necessary to design and construct a final closure cap for Phase II, Sequence 4
Project Manager: Sadhu S. Sandhu     send an email
Alternate Manager: Thomas J. Smith     
Agency Name: Public Works QPR?: Yes
Magisterial District: Coles
Original Budget: $3,638,075.00

Revised Budget:

$3,638,075.00
Original Start Date: 8/1/2017

Revised Start Date:

Original End Date: 11/30/2018

Revised End Date:

Last Updated On: 6/12/2018 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Solid Waste Fees/Closure Account

$3,638,075.00 --- 7/1/2017
       
Total Amount: $3,638,075.00 $3,638,075.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design 8/1/2017 1/31/2018    
2. Invitation for Bid (Neogotiate Contract) 12/1/2017 3/31/2018    
3. Construction 4/1/2018 11/30/2018    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue
8/15/2017Cap installation is required by State and Federal regulations within 180 days after the final elevation is achieved.

2. Schedule/Timing Issues     

 

Date

Issue
6/12/2018Contract was awarded to Sargent Corporation on February 28, 2018 with a notice to proceed for April 9, 2018. Contractor is preparing the sub-base for liner placement next week. Project is anticipated to be completed by December 10, 2018.

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue