Project Detail
Project Main Menu

Project Overview
Project Name: DPR:Generals Ridge Slope Repair (Project# 18C13003)
Project Type:
Project Description: Repair of Steep Slope erosion at Generals Ridge.
Project Manager: Tracy L. Hannigan     send an email
Alternate Manager:     
Agency Name: Parks & Rec QPR?: Yes
Magisterial District: Coles
Original Budget: $225,000.00

Revised Budget:

$225,000.00
Original Start Date: 5/1/2017

Revised Start Date:

Original End Date: 12/30/2017

Revised End Date:

Last Updated On: 8/25/2017 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Building & Facility Capital Program - FY2018 Allocation

$225,000.00 --- 7/1/2017
       
Total Amount: $225,000.00 $225,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Conducted site meeting on 5/5/17 with JMT engineers and Billy Casper Golf representatives to discuss design layout, construction access, and timeline. 5/5/2017 5/5/2017 Matt White  
2. JMT revised plans and submitted to City of Manassas Community Development Director, awaiting comment. 6/5/2017 6/5/2017 Matt White  
3. City of Manassas Park has reviewed plans, no technical comments. Only outstanding comment is to identify the City of Manassas Park as the owner. 8/21/2017 8/21/2017 Matt White  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
8/7/2017Manassas Park was contacted on 8/7/17 to find out when they would have comments back on plans. They thought PWC would review the plans because of the cover sheet of the plans. Manassas Park started to review the plans shortly afterwards.

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue