Project Name: DPR:Chinn Rec Center Repair (Project#18C13007)
Project Type:
Project Description: Chinn Rec Center Repairs. (Gas fired boiler replacement, Roof completion and HVAC Rooftop unit for the gym replacement)
Project Manager: Tracy L. Hannigan     send an email
Alternate Manager:     
Agency Name: Parks & Rec QPR?: Yes
Magisterial District: Occoquan
Original Budget: $725,000.00

Revised Budget:

$725,000.00
Original Start Date: 7/1/2017

Revised Start Date:

Original End Date: 12/30/2018

Revised End Date:

Last Updated On: 3/15/2019 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Building & Facility Capital Program - FY2018 Allocation

$725,000.00 --- 7/1/2017
       
Total Amount: $725,000.00 $725,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. PO for Roof Replacement issued 9/18/17. Expect work to occur during November. (Start date 11/7/17) 9/8/2017 11/7/2017 Ron Lilley  
2. Pricing for boilers received 9/29 ($342K), and PO is issued. Work to start on 11/3/17 and finish by mid December. 9/29/2017 12/15/2017 Ron Lilley  
3. Gym RTU pricing received $191K. Pricing being reviewed by Parks Staff. 11/1/2017 11/1/2017 Ron Lilley  
4. Roof replacement completed 12/8/2017 12/8/2017 12/8/2017 Ron Lilley  
5. PO issued to Paschen Johnson for gym RTU replacement in the amount of $185K 1/12/2018 1/12/2018 Ron Lilley  
6. Boiler replacement completed 1/15/2018 1/15/2018 1/15/2018 Ron Lilley  
7. Chinn Boilers complete 6/4/2018 6/4/2018 Gary Rzepecki  
8. Locker Room repairs – Complete 6/4/2018 6/4/2018 Gary Rzepecki  
9. Chinn Gym RTU – Contractor to confirm delivery date for new equipment and schedule installation. Looks like July. 6/4/2018 7/30/2018 Gary Rzepecki  
10. •Delivery & installation expected to be completed last week of August. •Unit installed; AC working as stand-alone, heating connections will follow this month. 8/1/2018 10/1/2018  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
1/2/2018Delay with boiler replacement due to delay in shipment of boiler.