Project Name: DPR:Chinn Rec Center Repair (Project#18C13007)
Project Type:
Project Description: Chinn Rec Center Repairs. (Gas fired boiler replacement, Roof completion and HVAC Rooftop unit for the gym replacement)
Project Manager: Tracy L. Hannigan     send an email
Alternate Manager:     
Agency Name: Parks & Rec QPR?: Yes
Magisterial District: Occoquan
Original Budget: $515,000.00

Revised Budget:

$515,000.00
Original Start Date: 7/1/2017

Revised Start Date:

Original End Date: 12/30/2017

Revised End Date:

Last Updated On: 8/17/2017 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Building & Facility Capital Program - FY2018 Allocation

$515,000.00 --- 7/1/2017
       
Total Amount: $515,000.00 $515,000.00


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue