Project Name: DPR:Splashdown Filters (Project#18C13009)
Project Type:
Project Description: Replace sediment filters. (Plunge, Activity/Leisure, Kiddie Pool, Lazy River)
Project Manager: Tracy L. Hannigan     send an email
Alternate Manager:     
Agency Name: Parks & Rec QPR?: Yes
Magisterial District: Gainesville
Original Budget: $375,000.00

Revised Budget:

$375,000.00
Original Start Date: 7/1/2017

Revised Start Date:

Original End Date: 4/30/2018

Revised End Date:

Last Updated On: 2/16/2018 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Building & Facility Capital Program - FY2018 Allocation

$375,000.00 --- 7/1/2017
       
Total Amount: $375,000.00 $375,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Met with Pool contractor to develop the scope of work on 9-22-17. Phase I will be evaluation of existing system •PO for evaluation issued on 10/26/17 9/22/2017 11/30/2017 Amarjit Riat  
2. •Draft design received on November 30th, under review •Comments submitted to AE on December 15th for revision to design. 11/30/2017 12/15/2017 Amarjit Riat  
3. PO issued for $215,508 for replacement of filters for Activity/Leisure Pool. Work expected to begin April 2018 2/1/2018 4/30/2018 Amarjit Riat  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue