Project Detail
Project Main Menu

Project Overview
Project Name: DPR:ADA Compliance (Project# 18C13001)
Project Type:
Project Description: Repair Parks for legal compliance with ADA law.
Project Manager: Tracy L. Hannigan     send an email
Alternate Manager:     
Agency Name: Parks and Rec QPR?: Yes
Magisterial District: Brentsville, Coles, Potomac, Gainesville, Neabsco, Occoquan, Woodbridge
Original Budget: $348,305.00

Revised Budget:

$348,305.00
Original Start Date: 7/1/2017

Revised Start Date:

Original End Date: 12/30/2018

Revised End Date:

Last Updated On: 6/14/2018 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Building & Facility Capital Program - FY2018 Allocation

$348,305.00 --- 7/1/2017
       
Total Amount: $348,305.00 $348,305.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Reviewing all ADA Survey's, contacting A/E firm for design work. *Facilities Management addressing restroom ADA issues. Work Order issued. 8/1/2017 8/1/2017 Amarjit Riat  
2. Met with AE firm, Michel Baker on September 21, 2017 to design the upgrade for Waterworks at Andrew Leitch Park per survey work previously completed. Received proposal 10/2/17 . Parks Staff is reviewing. 9/21/2017 10/2/2017 Amarjit Riat  
3. Waiting on Purchasing to finalize the contract with Baker International in order to process PO. *PO Issued 11/14/2017 10/2/2017 11/14/2017 Amarjit Riat  
4. AE completed the site survey work December 13th, 2017 12/13/2017 12/13/2017 Amarjit Riat  
5. Final comments submitted to AE 1-18-18 for Waterworks. •Met with A/E for final review on 1-26-18 1/18/2018 1/26/2018 Amarjit Riat  
6. Received final plans for Waterworks and Ben Lomond Park February 23, 2018. Ben Lomond Plans submitted to DSB for approval on 2-28-18 2/23/2018 2/28/2018 Amarjit Riat  
7. PO processed on 3-27-18 for the construction work at Ben Lomond Park. Work is in progress will be completed by May 7, 2018. Construction work in progress at Andrew Leitch Park at the North Parking Lot and Bathrooms and, will be completed by May 10, 2018. 3/27/2018 5/10/2018 Amarjit Riat  
8. Met with Finley on March 29, 2018 for cost estimation for the south Parking lot work and access to baseball fields, at Andrew Leitch Park. Proposal received form Finley April 23, 2018 for $176,733. Work expected to begin by May 15 and completed by May 27, 2018 3/29/2018 5/27/2018 Amarjit Riat  
9. ADA work (Paving and sidewalk)at Ben Lomond and Bathroom renovations, sidewalk and parking at Andrew Leitch Park completed May 24, 2018. Additional paving and parking south parking lot work will be completed during September 2018 under JOC work. 5/24/2018 9/1/2018 Amarjit Riat  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue