Project Name: DPR:Fuller Heights Park (Project# 16C13016)
Project Type:
Project Description: Stormwater Management
Project Manager: Tracy L. Hannigan     send an email
Alternate Manager:     
Agency Name: Parks & Rec QPR?: Yes
Magisterial District: Potomac
Original Budget: $168,723.46

Revised Budget:

$164,796.46
Original Start Date: 6/1/2016

Revised Start Date:

Original End Date: 12/30/2018

Revised End Date:

Last Updated On: 6/14/2018 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. General Fund

$164,796.46 --- 7/1/2015
       
Total Amount: $164,796.46 $164,796.46



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. A meeting between the Watershed and Parks Dept. was held on site on 5/18/17 to review the existing conditions and to resolve Mike Williamís (resident 18619 Old Triangle Road) complaint. 5/18/2017 5/18/2017 Amarjit Riat  
2. Met with Site Works on May 24, 2017 for cost proposal to raise the bio-retentions structures, and remove sediment. AECOM now proposing best method to pipe water into sewer system. Site Works completed work on June 30, 2017. 5/24/2017 6/30/2017 Amarjit Riat  
3. AECOM proposal received May 31, 2017 under review. Task Order signed on 6/6/17 $84,793 to look at two options on diverting the water. 30 Calendar days after NTP. PO issued on 6/8/17 5/31/2017 6/8/2017 Amarjit Riat  
4. Site Works will be installing four check dams at the outfall to slow down the storm water by July 14, 2017 7/14/2017 7/14/2017 Amarjit Riat  
5. AECOM will submit analysis of storm water diversion by July 19, 2017. 7/19/2017 7/19/2017 Amarjit Riat  
6. A meeting is scheduled with Watershed and AECOM on August 11, 2017 to discuss the storm water analysis. 8/11/2017 8/11/2017 Amarjit Riat  
7. AECOM delivered a new proposal on 10/3/17. Parks Staff reviewing. 10/3/2017 10/3/2017 Amarjit Riat  
8. A meeting with Supervisor Caddigan and Mr. Williams and Mr. Rand, Marc Aveni and Parks Staff and County Attorney on 4/20/2018. 4/20/2018 4/20/2018 Amarjit Riat  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue
6/4/2018Parks will be able to proceed with the plan to pipe the water into the VDOT storm water system. Easements will have to be, acquired. Parks will work with a JOC contractor to repair existing broken pipes to alleviate some of the excess water problem. We have a quote that needs updating and we have Mr. Randís permission since it is on his property. Design work will start when money is made available.

4. Impact on Other Projects     

 

Date

Issue