Project Name: FCM: ADC Main Building Repairs 20C60001
Project Type: Repairs
Project Description: The project provides repairs to the inmate housing areas on the second and third floors of the main jail building. Repairs include plumbing fixtures, security systems, heating, ventilation, and air conditioning (HVAC), furniture, and other maintenance systems that require updates. The Main Building is the original building at the ADC complex built in 1982.
Project Manager: Karen L. FitzGibbon     send an email
Alternate Manager: Eric Brunner     
Agency Name: Adult Detention Center QPR?: Yes
Magisterial District: Brentsville
Original Budget: $7,500,000.00

Revised Budget:

$7,500,000.00
Original Start Date: 7/1/2019

Revised Start Date:

Original End Date: 12/31/2021

Revised End Date:

Last Updated On: 8/19/2022 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. ADC Main Bldg Repairs - FY20 (CAD20002)

$6,997,500.00 --- 7/1/2019

2. City of Manassas Reimbursement - ADC Main Bldg Repairs (COL20001)

$502,500.00 --- 7/1/2019
       
Total Amount: $7,500,000.00 $7,500,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Roof replacement 3/1/2021 7/31/2021 5/31/2021    
2. Epoxy showers 3/1/2021 8/31/2021 6/30/2021    
3. Replace toilet/sink combos 3/1/2021 9/30/2021 6/30/2021    
4. Replace cell lights 6/1/2021 10/31/2021    
5. Replace HVAC vents 6/1/2021 10/31/2021    
6. Replace bunks 6/1/2021 10/31/2021    
7. Replace cell doors 6/1/2021 10/31/2021    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue