Project Name: SW: Landfill Cap Design and Construction of Existing Landfill Cell
Project Type: Landfill Project
Project Description: The project includes all work necessary to design and construct a final closure cap for the remaining portion of the existing landfill cell including vertical expansion
Project Manager: Sadhu S. Sandhu     send an email
Alternate Manager: Thomas J. Smith     
Agency Name: QPR?: Yes
Magisterial District: Coles
Original Budget: $3,300,000.00

Revised Budget:

$1,365,700.00
Original Start Date: 7/1/2001

Revised Start Date:

7/1/2001
Original End Date: 12/31/2002

Revised End Date:

9/30/2003
Last Updated On: 8/10/2006 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Solid Waste Fees

$3,300,000.00 $1,365,700.00 7/1/2001
       
Total Amount: $3,300,000.00 $1,365,700.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design 7/1/2001 1/15/2002 12/7/2002    
2. Invitation for Bid (Neogotiate Agreement with Anderson) 2/1/2002 10/1/2001 4/2/2002 1/22/2002    
3. Construction 5/1/2002 12/17/2001 12/1/2002 9/30/2003    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue