Project Detail
Project Main Menu

Project Overview
Project Name: OIT: Public Safety 800 MHz Digital Trunked Radio System
Project Type: Radio Communications
Project Description: This project installs a trunked radio communications system including the radio infrastructure and replacement of mobile and portable radios. The radio system provides a digital, trunked, and simulcast radio communications system in support of public safety and other government two-way radio users.
Project Manager: Victor R. Shavers     send an email
Alternate Manager:     
Agency Name: OIT/Radio Communications QPR?: Yes
Magisterial District: Brentsville, Coles, Potomac, Gainesville, Neabsco, Occoquan, Woodbridge
Original Budget: $20,190,758.00

Revised Budget:

$19,339,595.00
Original Start Date: 2/1/1993

Revised Start Date:

2/1/1997
Original End Date: 3/1/1996

Revised End Date:

8/12/2003
Last Updated On: 5/2/2004 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Delinquent Taxes and Fire Levy

$20,190,758.00 $19,339,595.00
       
Total Amount: $20,190,758.00 $19,339,595.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. BOCS approved continuing the project 2/1/1997 2/1/1997    
2. Phase III - Coverage Contours and Final System Design (OMNICOM/RCC Consultants) 11/1/1997 2/1/1998    
3. Review Final Sites with Citizen's Committee 2/1/1998 2/1/1998    
4. BOCS Approve Tower Sites/Procurement 2/1/1998 2/1/1998    
5. Develop Radio System Agreement & SOW (OMNICOM/RCC Consultants) 2/1/1998 4/1/1999    
6. Contract Negotiations 4/1/1998 9/1/1999    
7. Contract Award (BOCS) 4/1/1999 12/1/1999    
8. Apply/FAA/FCC/Planning Licenses & Permits 8/1/1998 8/1/2000    
9. Approve Revised Site Plans - Planning Commission 8/1/1998 5/1/2000    
10. Build Infrastructure 4/1/2001 6/1/2002    
11. Infrastructure Proof of Performance Test 7/1/2002 8/1/2002    
12. Install Radio Mobiles and Portables 3/26/2003 7/2/2003    
13. Final System Implementation (Vendor) 2/1/2003 3/1/2003    
14. System Acceptance Testing 7/3/2003 8/5/2003    
15. System Acceptance 8/12/2003 8/12/2003    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue