Project Detail
Project Main Menu

Project Overview
Project Name: HP: Rippon Lodge Historic Site
Project Type: General stabilization and restoration
Project Description: Stabilize and restore Rippon Lodge Historic Site for public use.
Project Manager: Barbara A. Rahll     send an email
Alternate Manager: Ray M. Goodrow     
Agency Name: Public Works QPR?: Yes
Magisterial District: Woodbridge
Original Budget: $2,037,145.00

Revised Budget:

$2,037,145.00
Original Start Date: 11/1/2000

Revised Start Date:

Original End Date: 12/31/2005

Revised End Date:

12/31/2008
Last Updated On: 11/14/2008 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. FY09 CIP Budget

$70,000.00 --- 7/1/2008

2. State Grant 2007

$5,000.00 $5,000.00 7/1/2007

3. FY08 CIP Budget

$70,000.00 $70,000.00 7/1/2007

4. State Grant FY07

$10,000.00 --- 6/30/2007

5. FY07 CIP Budget

$70,000.00 --- 7/1/2006

6. State Grant FY06

$50,000.00 --- 7/1/2005

7. William Center Funding

$1,225,000.00 --- 8/6/2002

8. VDOT TEA-21 Grant (2002)

$50,000.00 --- 7/18/2002

9. Dept of Historic Resources CLG Grant

$17,145.00 --- 7/1/2002

10. FY 01-02 Carryover Funding

$300,000.00 --- 9/30/2001

11. FY02 CIP Budget

$170,000.00 --- 7/1/2001
       
Total Amount: $2,037,145.00 $2,037,145.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
Number
of Hours
1. Expansion of the 1970s garage to accommodate archaeology lab, public toilets and volunteer lounge 4/1/2006 6/1/2006 12/31/2007
2. Improvements to "Barn" on site to accommodate woodshop and work space for carpenters 8/1/2006 12/31/2006 12/31/2007
3. Water Line extension 6/1/2007 6/1/2008 9/30/2007 9/30/2008 Goodrow 65
4. Fencing and signage 3/1/2008 9/30/2008 Rahll 75


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue
1/3/2008Rippon Lodge will open on May 3, 2008. The hours will be from 11:00 to 4:00 on weekends through October 2008.

2. Schedule/Timing Issues     

 

Date

Issue
2/15/2008Easements for water line access across the neighboring parcel are being reviewed by the County Attorney and the adjacent landowner.

3. Fiscal/Resource Issues     

 

Date

Issue
1/3/2008Staff is reviewing the estimated cost for the garage expansion. The expansion project will be completed with in house staff. It is expected that the project will start in September 2008.

4. Impact on Other Projects     

 

Date

Issue