Project Detail
Project Main Menu

Project Overview
Project Name: FC: Phase III Administration Building
Project Type: New Facility Construction
Project Description: 100,000 s.f. office space for Public Works, Planning and OIT with 33,000 s.f. existing space renovation.
Project Manager: Seena Vasan     send an email
Alternate Manager: Mohamed E. Abdelrahim     
Agency Name: Public Works QPR?: Yes
Magisterial District: Coles
Original Budget: $2,889,925.00

Revised Budget:

$45,853,257.00
Original Start Date: 1/8/2002

Revised Start Date:

3/15/2002
Original End Date: 6/15/2006

Revised End Date:

1/31/2007
Last Updated On: 1/28/2008 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. 1. General Fund - Debt Financing

$2,889,925.00 $45,853,257.00 4/15/2003
       
Total Amount: $2,889,925.00 $45,853,257.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Planning 3/15/2002 10/1/2002    
2. RFP for Architecural Services 9/18/2002 3/14/2003    
3. A/E Contract Award 3/17/2003 3/17/2003    
4. Schematic Design 5/30/2003 10/9/2003    
5. Design Development and Construction Documents 10/10/2003 8/15/2004    
6. Permit Review 8/25/2004 10/25/2004 1/15/2005    
7. Bidding 11/1/2004 1/10/2005 12/15/2004 2/23/2005    
8. Construction 12/21/2004 3/22/2005 3/15/2006 6/30/2006    
9. Punchlist 2/15/2006 6/30/2006 3/15/2006 7/31/2006    
10. Occupancy 3/15/2006 10/1/2006 4/30/2006 12/31/2006    
11.    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue