Project Detail
Project Main Menu

Project Overview
Project Name: PM: Fleet Administrative Offices
Project Type: Construction
Project Description: Construct new Fleet Administrative Building (2400 SF)to house Fleet administrative staff, Building & Grounds storage, and an office area for the Building Operations Engineer. Various divisions within Public Works will be responsible for preparing site plans, clearing, grading, and moving utilities. Construction will be performed by Building and Grounds staff.
Project Manager: Said G. Said     send an email
Alternate Manager: Linda J. Winslow     
Agency Name: PW Property Management QPR?: Yes
Magisterial District: Coles
Original Budget: $150,000.00

Revised Budget:

$220,000.00
Original Start Date: 1/27/2003

Revised Start Date:

Original End Date: 4/30/2004

Revised End Date:

2/25/2005
Last Updated On: 4/19/2005 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Building and Grounds Base Budget

$100,000.00 $140,000.00 11/1/2004

2. CIP

$50,000.00 $80,000.00 7/15/2002
       
Total Amount: $150,000.00 $220,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. A/E Design 3/31/2003 9/1/2003 Moseley Architects  
2. Geotechnical Survey 4/28/2003 5/24/2003 Draper Aden  
3. Construction Plans 1st review 9/4/2003 10/20/2003 Bldg. Dev.  
4. Revise Plans per BD comments 10/22/2003 11/12/2003 1/9/2004 Moseley Architects  
5. Construction Plans 2nd Review 11/17/2003 1/13/2004 12/8/2003 1/30/2004 Bldg. Dev.  
6. Site Preparation, and building Pad 12/15/2003 4/5/2004 1/9/2004 4/23/2004 Contrator  
7. Construction of building foundation and slab 1/12/2004 5/10/2004 1/23/2004 5/21/2004 PM  
8. Construction of Building Structure 1/26/2004 5/25/2004 2/27/2004 8/20/2004 Contractor  
9. Interior construction and finish 3/1/2004 8/23/2004 4/23/2004 12/30/2004 B&G  
10. Systems Furniture Installation 4/15/2004 2/14/2005 4/20/2004 2/18/2005 Contractor &PM  
11. Move and Project Closeout 4/26/2004 2/21/2005 4/30/2004 2/25/2005 PM  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
1/7/2005Water leaked through the control joints of the building slab. The Contractor cut the slab deeper than specified in some areas. Contractor repaired the slab per the structurural engineer's recommendations. PW added a french drain system around the building to enhance water drainge . This issue delayed the completion date of the project. Some minor changes in furnishing the building were requested by Fleet Admin.

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue