Project Detail
Project Main Menu

Project Overview
Project Name: TD: Montgomery Avenue
Project Type: Revenue Sharing - Sidewalk Construction
Project Description: Provide curb, gutter and a sidewalk on the eastbound lane of Montgomery Avenue(Route 1381)from Longview Drive (Route 1279) to Optiz Boulevard (Route 2000)
Project Manager: Thomas J. Blaser     send an email
Alternate Manager: Kafayat U. Rahmani     
Agency Name: Transportation Division of Public Works QPR?: Yes
Magisterial District: Woodbridge
Original Budget: $142,000.00

Revised Budget:

$637,687.00
Original Start Date: 6/1/2001

Revised Start Date:

3/11/2002
Original End Date: 6/30/2002

Revised End Date:

6/30/2002
Last Updated On: 4/26/2004 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. RES 02-242 BT from Rt 1 Sidewalk

$0.00 $100,000.00 4/2/2002

2. FY 98-99 thru FY02-03 Revenue Sharing Funds - State Allocation

$71,000.00 $229,442.00 7/1/1998

3. FY98-99 thru FY02-03 Revenue Sharing Funds - County Allocation

$71,000.00 $308,245.00 7/1/1998
       
Total Amount: $142,000.00 $637,687.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right-of-way Research 6/1/2001 6/30/2001    
2. Engineering Survey 7/1/2001 7/30/2001    
3. Engineering Design 8/1/2001 9/30/2001    
4. VDOT Review 10/1/2001 10/30/2001    
5. Addressing VDOT Comments 11/1/2001 12/30/2001    
6. VDOT Approval 1/1/2002 1/30/2002    
7. Right-of-way/Easements Acquisition 8/1/2001 2/28/2002    
8. Relocation of Utilities 3/1/2002 3/31/2002    
9. Construction 4/1/2002 6/30/2002    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue