Project Detail
Project Main Menu

Project Overview
Project Name: TD: Old Bridge Road Sidewalk
Project Type: Revenue Sharing - Sidewalk Construction
Project Description: Provide curb, gutter, and a sidewalk along the West-bound lane of Old Bridge Road between Smoketown Road and Westridge Drive.
Project Manager: Thomas J. Blaser     send an email
Alternate Manager: Kafayat U. Rahmani     
Agency Name: Transportation Division of Public Works QPR?: Yes
Magisterial District: Coles
Original Budget: $477,765.00

Revised Budget:

$540,098.00
Original Start Date: 1/1/2000

Revised Start Date:

Original End Date: 5/31/2002

Revised End Date:

8/31/2002
Last Updated On: 4/26/2004 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. FY97-98 thru FY02-03 Revenue Sharing Funds-State Allocation

$233,270.00 $263,788.00 7/1/1998

2. FY97-98 thru FY02-03 Revenue Sharing Funds-County Allocation

$244,495.00 $276,310.00 7/1/1998
       
Total Amount: $477,765.00 $540,098.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Engineering Survey 1/1/2000 4/30/2000    
2. Design 5/1/2000 8/31/2000    
3. VDOT Review 9/1/2000 1/31/2001    
4. Address VDOT Comments 1/1/2001 2/28/2001    
5. VDOT Approval of Design 3/1/2001 5/31/2001    
6. Right of Way Acquisition 6/1/2001 8/31/2001    
7. Utility Relocation 9/1/2001 10/31/2001    
8. Construction 11/1/2001 5/31/2002 8/31/2002    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue