Project Name: SW: Landfill Liner Design and Construction of Phase 1, Parts 3&4 Cells
Project Type: Landfill CIP Project
Project Description: The project includes all work necessary to design and construct Phase 1, Parts 3&4 lined cells at the Prince William County Sanitary Landfill at Independent Hill
Project Manager: Sadhu S. Sandhu     send an email
Alternate Manager: Thomas J. Smith     
Agency Name: QPR?: Yes
Magisterial District: Coles
Original Budget: $5,131,880.00

Revised Budget:

$4,442,033.00
Original Start Date: 7/1/2003

Revised Start Date:

Original End Date: 12/31/2005

Revised End Date:

5/1/2006
Last Updated On: 10/31/2006 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Construction - Solid Waste Fees and Revenue Bond Proceeds

$4,731,880.00 $3,985,033.00 7/1/2003

2. Construction Management - Solid Waste Fees

$300,000.00 $357,000.00 7/1/2003

3. Design - Solid Waste Fees

$100,000.00 $100,000.00 7/1/2002
       
Total Amount: $5,131,880.00 $4,442,033.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design-Phase I, Parts 3&4 7/1/2003 12/31/2003    
2. Invitation for Bid 11/1/2003 3/1/2004    
3. Construction-Phase I, Part 3 3/1/2004 3/25/2004 12/31/2004 9/20/2004    
4. Construction-Phase I, Part 4 7/1/2005 7/18/2005 12/31/2005 5/1/2006    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue