Project Detail
Project Main Menu

Project Overview
Project Name: Fire and Rescue CIP - Lake Jackson Station Renovation
Project Type: Renovation of an existing fire and rescue station.
Project Description: This project will expand the Lake Jackson Fire Station (#7) by increasing the size of living quarters for both male and female firefighters, office space, classroom facilities, and weight room. The station is located on Coles Drive and services the Lake Jackson, Brentsville, and Canova areas.
Project Manager: Steven Kersse     send an email
Alternate Manager: Donna M. Poillucci     
Agency Name: Fire and Rescue QPR?: Yes
Magisterial District: N/A
Original Budget: $4,108,805.00

Revised Budget:

$4,125,350.00
Original Start Date: 7/1/2002

Revised Start Date:

Original End Date: 6/30/2005

Revised End Date:

10/1/2006
Last Updated On: 4/10/2007 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Proffers Projected - FY 2007

$0.00 $16,545.00 7/1/2006

2. Fire and Rescue Levy - Prior Years

$1,880,000.00 --- 7/1/2005

3. Proffers/General Fund - Prior Years

$53,064.00 --- 7/1/2005

4. Debt - FY 2006

$2,020,000.00 --- 7/1/2005

5. Debt - Prior Years

$155,741.00 --- 7/1/2005
       
Total Amount: $4,108,805.00 $4,125,350.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Planning & Design 7/1/2002 6/30/2004    
2. Construction 7/1/2004 7/15/2005 6/30/2005 10/1/2006    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
1/22/2007Occupancy permit obtained and LJVFD has moved into the entire space. Minor punch list items still remain.
8/4/2006First phase of construction is completed and LJVFD moved into that space on 7/29/06. Second phase of construction is on it's way.
7/12/2006First Phase of construction is expected to be completed by 7/14/06. Second Phase has begun and is anticpated to end 10/06. Furniture is ordered.
10/13/2004Permit process is underway

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue