Project Detail
Project Main Menu

Project Overview
Project Name: DOT: Sudley Manor Drive Extended
Project Type: 2002 Road Bond
Project Description: A new four-lane divided facility with a generally depressed grass median that will extend Sudley Manor Drive for approximately 11,000 linear feet from Chatsworth Drive on a southwestern direction with a bridge over the Norfolk Southern Railroad and intersecting at grade with Prince William Parkway (Route 234 Bypass) and connecting with existing Sudley Manor Drive in the Victory lakes Area and to relocated Linton Hall Road.
Project Manager: Thomas J. Blaser     send an email
Alternate Manager: Khattab O. Shammout     
Agency Name: Department of Transportation QPR?: Yes
Magisterial District: Brentsville
Original Budget: $24,139,278.00

Revised Budget:

$37,408,002.00
Original Start Date: 7/1/2003

Revised Start Date:

Original End Date: 3/31/2007

Revised End Date:

12/15/2006
Last Updated On: 4/20/2009 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Proffers

$0.00 $1,243,478.00 7/27/2004

2. General Fund

$461,600.00 $11,453,608.00 7/27/2004

3. Capital Projects Fund

--- $1,650,084.00 7/1/2004

4. 2002 Road Bond

$23,677,678.00 $23,060,832.00 7/1/2004
       
Total Amount: $24,139,278.00 $37,408,002.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Engineering/Design 7/1/2003 7/1/2004 3/31/2004    
2. Design/Environmental/Right-of-Way 4/1/2004 9/30/2004    
3. Environmental/Right-of-Way 10/1/2004 12/31/2004    
4. Right-of-Way/Utility Relocation 1/1/2005 3/31/2005    
5. Utility relocation/Construction 4/1/2005 9/30/2005    
6. Construction 7/1/2004 7/1/2004 10/31/2006 12/15/2006    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue