Project Detail
Project Main Menu

Project Overview
Project Name: TD: Spruce Street Sidewalk
Project Type: Revenue Sharing
Project Description: Spruce Street Sidewalk - Construction of curb and gutter and sidewalk along .47 miles of Spruce Street (Route 1526). It will run from Centreville Road (Rt 28) to Old Centreville Road (Rt616)
Project Manager: Thomas J. Blaser     send an email
Alternate Manager: Kafayat U. Rahmani     
Agency Name: Transportation Division QPR?: Yes
Magisterial District: Brentsville
Original Budget: $2,856.00

Revised Budget:

$2,856.00
Original Start Date: 7/1/2003

Revised Start Date:

7/1/2004
Original End Date: 4/30/2006

Revised End Date:

9/30/2006
Last Updated On: 11/15/2004 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. FY03 State Allocation

$1,428.00 --- 7/1/2003

2. FY03 County Allocation

$1,428.00 --- 7/1/2003
       
Total Amount: $2,856.00 $2,856.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Engineering Survey & Design 7/1/2004 9/30/2004    
2. VDOT Approval 10/1/2004 12/31/2004    
3. Right-of-way & Easements Acquisition 1/1/2005 3/31/2005    
4. Relocation of Utilities 4/1/2005 6/30/2005    
5. Construction 7/1/2005 9/30/2005    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue