Project Name: ES: Gideon Square, Bisbee Court / Watershed: Neabsco Creek
Project Type: Drainage Improvement
Project Description: Stabilize eroded creek bank
Project Manager: Khalid Quraishi     send an email
Alternate Manager: Mukesh B. Patel     
Agency Name: Department of Public Works QPR?: Yes
Magisterial District: Neabsco
Original Budget: $80,000.00

Revised Budget:

$80,000.00
Original Start Date: 1/15/2004

Revised Start Date:

Original End Date: 9/30/2004

Revised End Date:

Last Updated On: 11/15/2004 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Stormwater Management/Drainage Fund

$80,000.00 ---
       
Total Amount: $80,000.00 $80,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right of Entry Agreement 1/15/2004 1/30/2004    
2. Field Survey, Design and Corps of Engineers review 1/30/2004 5/31/2004    
3. Construction Cost Estimate, Establish Purchase Order, and Issue of Task order 6/1/2004 7/30/2004    
4. Construction 8/20/2004 9/30/2004    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue