Project Detail
Project Main Menu

Project Overview
Project Name: ES: 15808-15814 Lazy Day Ln/Watershed: Powells Creek
Project Type: Drainage Improvement Project
Project Description: (Country Club, Section 2, Project Code Number: 5610) Storm water runoff is causing standing water, sogginess and flooding on the properties. Public Works will design and construct a drainage system to alleviate the problem.
Project Manager: Khalid Quraishi     send an email
Alternate Manager: Mukesh Patel     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Potomac
Original Budget: $25,000.00

Revised Budget:

$25,000.00
Original Start Date: 4/5/2004

Revised Start Date:

Original End Date: 1/31/2005

Revised End Date:

12/30/2005
Last Updated On: 4/6/2006 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. CIP

$25,000.00 ---
       
Total Amount: $25,000.00 $25,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right of Entry 4/5/2004 7/20/2004    
2. Field Survey 7/21/2004 8/24/2004 11/15/2004    
3. Design 9/24/2004 11/22/2004 11/12/2004 1/14/2005    
4. Design approval by homeowners 11/15/2004 1/14/2005 11/30/2004 10/28/2005    
5. Preparation of Task order and material purchase 12/20/2004 10/28/2005 1/31/2005 11/30/2005    
6. Construction 12/20/2004 11/30/2005 1/31/2005 12/30/2005    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue