Project Name: DOT: Wellington Road Widening
Project Type: 1998 County Road Bond
Project Description: This project includes improvements in two areas, western improvements in the vicinity of University Blvd/Progress Court and eastern improvements in the vicinity of Balls Ford Road and Devlin Road. On the western end, Wellington Road will be widened from approximately 900 feet east of University Blvd/Progress Court up to Virginia Gateway. The eastern improvements include realignment of Balls Ford and Devlin Roads in to a single intersection and the widening of Wellington Road between existing Balls Ford and Gainsford Court.
Project Manager: Thomas J. Blaser     send an email
Alternate Manager: Khattab O. Shammout     
Agency Name: Department of Transportation QPR?: Yes
Magisterial District: Brentsville
Original Budget: $5,158,293.00

Revised Budget:

$9,543,870.00
Original Start Date: 7/1/1999

Revised Start Date:

Original End Date: 12/31/2004

Revised End Date:

9/30/2006
Last Updated On: 1/20/2007 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. 1998 County Road Bond

$5,106,309.00 $5,202,192.00 7/1/1999

2. Proffer Funds

$51,984.00 $0.00

3. Expenditure Reimbursement

$0.00 $57,515.00

4. Transfer From General Fund

$0.00 $4,284,163.00
       
Total Amount: $5,158,293.00 $9,543,870.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design 8/15/2002 8/15/2002 8/30/2003 4/11/2005    
2. Right of way acquisition 7/1/2003 10/1/2004 1/31/2004 10/31/2004    
3. Utility Relocation 1/31/2004 10/31/2004 12/15/2004 11/12/2005    
4. Construction 1/1/2004 6/17/2005 12/31/2004 9/30/2006    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
8/1/2205The notice to proceed with construction of the project was given on 6/17/2005. The project is proceeding within schedule and budget.

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue