Project Name: ES: Clipper-Skipper Drive Phase II/Watershed: Occoquan River
Project Type: Drainage Improvement Project
Project Description: (Project Code Number: 5622) A rusted corrugated metal pipe was replaced as part of the Phase I project. The dilapidated cinder block structure and the rusted metal pipe upstream of Phase I will be replaced.
Project Manager: Khalid Quraishi     send an email
Alternate Manager: Mukesh Patel     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Occoquan
Original Budget: $60,000.00

Revised Budget:

$65,000.00
Original Start Date: 9/15/2004

Revised Start Date:

Original End Date: 4/29/2005

Revised End Date:

Last Updated On: 4/20/2005 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Stormwater Management/Drainage Funds

$60,000.00 $65,000.00
       
Total Amount: $60,000.00 $65,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right of Entry 9/15/2004 9/15/2004    
2. Design of the junction box 9/15/2004 10/4/2004    
3. Material (Fabrication of a junction box)/Work Order Preparation 10/4/2004 12/29/2004    
4. Construction 1/14/2005 4/29/2005    
5.    
6.    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue