Project Detail
Project Main Menu

Project Overview
Project Name: ES: 1438 Flagship Drive/Occoquan River
Project Type: Drainage Improvement Project
Project Description: (Project Code Number: 5630 ) Storm water runoff is causing standing water, sogginess and basement flooding. Public Works will design and construct a drainage system to alleviate the problem.
Project Manager: Khalid Quraishi     send an email
Alternate Manager: Mukesh B. Patel     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Occoquan
Original Budget: $10,000.00

Revised Budget:

$10,000.00
Original Start Date: 9/30/2004

Revised Start Date:

Original End Date: 12/29/2004

Revised End Date:

Last Updated On: 1/28/2005 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. CIP

$10,000.00 ---
       
Total Amount: $10,000.00 $10,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right of Entry 9/30/2004 11/15/2004    
2. Construction 12/1/2004 12/29/2004    
3.    
4.    
5.    
6.    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue