Project Detail
Project Main Menu

Project Overview
Project Name: ES: Rippon Boulevard Landscape Plantings
Project Type: Landscaping
Project Description: The project consists of landscaping plantings within the median areas along Rippon Boulevard. The plantings will include the installation of four flower beds consisting of Parson Juniper, Blue Rug Juniper and Dwarf Red Barberry.
Project Manager: Wade A. Hugh     send an email
Alternate Manager:     
Agency Name: Public Works QPR?: Yes
Magisterial District: Woodbridge
Original Budget: $20,000.00

Revised Budget:

$7,500.00
Original Start Date: 1/1/2005

Revised Start Date:

Original End Date: 12/31/2006

Revised End Date:

9/30/2005
Last Updated On: 1/31/2006 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. General Fund - Landscape budgets

$20,000.00 $7,500.00
       
Total Amount: $20,000.00 $7,500.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design 1/1/2005 2/1/2005    
2. VDOT Permit 2/1/2005 3/1/2005 3/2/2005    
3. Planting 7/1/2005 12/31/2006 9/30/2005    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue