Project Detail
Project Main Menu

Project Overview
Project Name: DOT: Cardinal Drive Sidewalk
Project Type: Revenue Sharing Project
Project Description: Installing .44 miles of sidewalk on North side of Cardinal Drive from Minnieville Road to Redwing Drive.
Project Manager: Thomas J. Blaser     send an email
Alternate Manager: Kafayat U. Rahmani     
Agency Name: Department of Transportation QPR?: Yes
Magisterial District: Neabsco
Original Budget: $137,588.00

Revised Budget:

$137,588.00
Original Start Date: 4/1/2005

Revised Start Date:

Original End Date: 6/30/2006

Revised End Date:

8/31/2006
Last Updated On: 1/20/2007 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. FY2004-05 State Allocation

$68,794.00 --- 7/1/2004

2. FY 2004-05 County Allocation

$68,794.00 --- 7/1/2004
       
Total Amount: $137,588.00 $137,588.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design 4/1/2005 6/30/2005    
2. VDOT Approval 7/1/2005 9/30/2005    
3. Acquisition of Right-of-way & Easements 10/1/2005 12/31/2005 1/1/2006    
4. Relocation of Utilities 2/1/2006 4/30/2006    
5. Construction 9/1/2006 5/1/2006 12/31/2006 8/31/2006    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue