Project Detail
Project Main Menu

Project Overview
Project Name: FC: Judicial Center Expansion
Project Type: New Facility Construction
Project Description: The Judicial Center Expansion will expand the existing facility by 39,000 square feet to provide six (6) additional courtrooms.
Project Manager: LouAnn D. Purkins     send an email
Alternate Manager: Seena Vasan     
Agency Name: Department of Public Works QPR?: Yes
Magisterial District: Brentsville
Original Budget: $17,590,480.00

Revised Budget:

$19,151,931.00
Original Start Date: 3/1/2000

Revised Start Date:

Original End Date: 7/1/2004

Revised End Date:

11/13/2004
Last Updated On: 1/19/2006 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. General Fund - Debt Financing

$17,590,480.00 $19,151,931.00
       
Total Amount: $17,590,480.00 $19,151,931.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Design 3/1/2000 10/1/2001  
2. Permit Review 10/1/2001 12/1/2001  
3. Bidding 1/1/2002 3/1/2002 5/3/2002 Purchasing  
4. Contract Award 4/1/2002 4/1/2002 6/4/2002  
5. Construction (Expansion) 4/1/2002 6/17/2002 10/1/2003 1/8/2004 PW - FCM  
6. Punchlist (Expansion) 10/1/2003 1/12/2004 11/1/2003 5/7/2004 PW- FCM  
7. Occupancy 12/1/2003 2/16/2004 2/9/2004 3/12/2004 PW - Prop Mgmt  
8. Construction (Expansion/ Existing Building) 1/1/2004 1/24/2004 6/1/2004 10/9/2004 PW - FCM  
9. Punchlist (Expansion/ Existing Building) 7/20/2004 6/19/2004 8/19/2004 11/13/2004 PW - FCM  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue
1/13/2005Construction Contract documents for a new effort to provide a 90 space parking lot are complete. The Lot will be located adjacent to and north of the parking lot that was provided under this project. This Lot will replace the parking spaces that will be eliminated by the construction of the ADC Expansion Project. Parking in the new parking lot is scheduled to be available by July 2005 when construction for the ADC project is scheduled to begin. Actions to define and address additional requirements for the Security System and changes to the General District Court Fine Paying Station are underway.