Project Detail
Project Main Menu

Project Overview
Project Name: PA: Prince William Golf Course Renovation
Project Type: Renovation
Project Description: The Park Authority will renovate the existing 18-hole Prince William Golf Course off of Vint Hill Road. The Park Authority began operating this facility in-house as of November 2002. Renovations to the existing 18-hole course are proposed to enhance its marketability. Replacement of existing irrigation system.
Project Manager: John Lyons     send an email
Alternate Manager:     
Agency Name: Park Authority QPR?: Yes
Magisterial District: Brentsville
Original Budget: $760,000.00

Revised Budget:

$760,000.00
Original Start Date: 8/1/2002

Revised Start Date:

10/15/2005
Original End Date: 8/1/2004

Revised End Date:

9/30/2007
Last Updated On: 4/12/2007 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Debt FY05 County

$660,000.00 --- 7/1/2005

2. PWCPA Contribution

$100,000.00 --- 7/1/2005
       
Total Amount: $760,000.00 $760,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Golf Course Renovations - Irrigation, Pond Rev. Pump House 11/1/2003 10/15/2005 8/1/2004 7/1/2006    
2. Club House Renovations 5/30/2006 1/15/2007    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
1/30/2006Construction of the irrigation system is planned to start on February 1, 2006
7/22/2005Irrigation drawings and specifications sent to irrigation engineer for review and revisions.
6/3/2005Task order issued to Draper Aden Associates weith notice to proceed on design and permit phase.
1/13/2005Schedule has been revised to reflect new funding timeline and to lessen impact on the business of the facility.
7/29/2004Awaiting approval of financing prior to moving forward on irrigation and clubhouse renovations.

3. Fiscal/Resource Issues     

 

Date

Issue
1/13/2005Pending approval and issuance of debt financing.

4. Impact on Other Projects     

 

Date

Issue