Project Detail
Project Main Menu

Project Overview
Project Name: FC: Juvenile Detention Home Expansion - Phase II
Project Type: New Facility Construction
Project Description: The new construction will include an 11,000 square foot addition to the existing facility to provide 32 single occupancy bedrooms and two classrooms with storage. Renovations will include the existing kitchen, staff offices, lobby and visitors area.
Project Manager: LouAnn D. Purkins     send an email
Alternate Manager: Seena Vasan     
Agency Name: Department of Public Works QPR?: Yes
Magisterial District: Coles
Original Budget: $6,448,250.00

Revised Budget:

$6,448,250.00
Original Start Date: 2/1/1998

Revised Start Date:

Original End Date: 2/1/2003

Revised End Date:

3/15/2004
Last Updated On: 5/2/2004 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. FY 97 Carry over funds

$300,000.00 --- 8/1/1997

2. Bond Funds

$6,148,250.00 ---
       
Total Amount: $6,448,250.00 $6,448,250.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Hire Architect 2/1/1998 10/1/1998    
2. Design 10/1/1998 12/1/1999    
3. Review by State and County 1/1/2000 10/1/2000    
4. Bidding 10/1/2000 4/1/2001    
5. Construction 7/1/2001 1/1/2003    
6. Punchlist 12/1/2002 12/27/2002 1/1/2003 1/31/2003    
7. Move-In 2/1/2003 7/17/2003 7/24/2003    
8. Security System Enhancements 10/6/2003 3/15/2004    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue