Project Detail
Project Main Menu

Project Overview
Project Name: PM: Owens Building Expansion
Project Type: New Facility Construction
Project Description: The building will expand by 13,300 square feet to accomodate growth for the current occupants (Office of Public Safety) and OIT.
Project Manager: Mohamed E. Abdelrahim     send an email
Alternate Manager: LouAnn D. Purkins     
Agency Name: Department of Public Works QPR?: Yes
Magisterial District: Coles
Original Budget: $5,343,850.00

Revised Budget:

$5,343,850.00
Original Start Date: 5/1/2000

Revised Start Date:

Original End Date: 12/2/2002

Revised End Date:

6/1/2003
Last Updated On: 5/2/2004 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Debt Financing

$5,343,850.00 ---
       
Total Amount: $5,343,850.00 $5,343,850.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design 5/1/2000 9/1/2001    
2. Permit Review 9/1/2001 11/1/2001    
3. Bidding 12/1/2001 1/1/2002    
4. Contract Award 2/1/2002 2/1/2002    
5. Construction 2/1/2002 2/1/2002 7/20/2002    
6. Construction of Tenant Fitout (Shell Building) 7/20/2002 9/23/2002 8/30/2002 12/10/2002    
7. Occupancy (Expansion only.) 12/1/2002 8/30/2002 12/1/2002 12/15/2002    
8. Design of Backfill    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue