Project Name: ES: 11319 Hazelwood Drive / Watershed: Cedar Run
Project Type: Drainage Improvement Project
Project Description: (Project Code Number: 5669 ) The property owners are experiencing flooding in their backyard. Public Works will design and construct a drainage system to alleviate the problem.
Project Manager: Khalid Quraishi     send an email
Alternate Manager: Mukesh B. Patel     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Brentsville
Original Budget: $20,000.00

Revised Budget:

$45,000.00
Original Start Date: 10/3/2005

Revised Start Date:

Original End Date: 3/31/2006

Revised End Date:

9/29/2006
Last Updated On: 1/16/2007 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. CIP

$20,000.00 $45,000.00
       
Total Amount: $20,000.00 $45,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right of Entry 10/3/2005 10/25/2005    
2. Field Survey by A/E contractor 11/25/2005 12/30/2005    
3. Design & its review by the property owner 12/30/2005 1/31/2006    
4. Corps of Engineer Permit 1/31/2006 7/31/2006    
5. Construction task order and allocation of funds 7/31/2006 8/31/2006    
6. Construction 8/31/2006 9/29/2006    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue