Project Detail
Project Main Menu

Project Overview
Project Name: DOT: Dale Boulevard Sidewalk Ashdale Avenue to Gideon Drive
Project Type: Revenue Sharing & TRIP Funds - Sidewalk Construction
Project Description: Provide sidewalk, curb and gutter on the north side of Dale Boulevard (Route 784) from Ashdale Avenue (Route 1801) to Gideon Drive (Route 2068)
Project Manager: Khattab O. Shammout     send an email
Alternate Manager: Kafayat U. Rahmani     
Agency Name: Department of Transportation QPR?: Yes
Magisterial District: Neabsco
Original Budget: $342,666.00

Revised Budget:

$342,666.00
Original Start Date: 8/1/2006

Revised Start Date:

Original End Date: 3/31/2008

Revised End Date:

5/31/2008
Last Updated On: 11/21/2008 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. FY 2007 TRIP Funds

$250,000.00 --- 9/1/2006

2. FY06 County Allocation

$80,357.00 --- 7/1/2005

3. Transfer from OCA 400194

$12,309.00 ---
       
Total Amount: $342,666.00 $342,666.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right-of-way Research 8/1/2006 8/15/2006    
2. Engineering Survey 8/16/2006 8/31/2006    
3. Engineering Design 9/1/2006 12/31/2006 8/31/2007    
4. VDOT Approval 1/1/2007 2/1/2007 4/30/2007 12/3/2007    
5. Right-of-way/Easements Acquisition 5/1/2007 7/31/2007    
6. Relocation of Utilities 8/1/2007 10/31/2007    
7. Construction 11/1/2007 2/11/2008 3/31/2008 5/31/2008    
8.    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue