Project Detail
Project Main Menu

Project Overview
Project Name: BG: Owens Building Structural Repairs
Project Type: Structural Repairs
Project Description: The Owens Building has been subject to roof leaks and structural defects that have allowed water penetration since construction. Temporary repairs reduced the potential for damage; however, this is a key facility and it is necessary to have the building water tight and effective as an emergency operation center.
Project Manager: Robert M. Weiss     send an email
Alternate Manager: Don H. Flory     
Agency Name: DPW/Buildings & Grounds QPR?: Yes
Magisterial District: Coles
Original Budget: $282,500.00

Revised Budget:

$599,855.00
Original Start Date: 1/2/2000

Revised Start Date:

Original End Date: 6/30/2003

Revised End Date:

4/9/2004
Last Updated On: 7/12/2004 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. CIP -- General Fund

$282,500.00 $599,855.00 6/24/2003
       
Total Amount: $282,500.00 $599,855.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Engineering Analysis 4/1/2001 12/1/2002 2/15/2003    
2. IFB Preparation 1/1/2002 3/3/2003 8/1/2002 6/1/2003    
3. Anticipated Award 8/1/2002 6/1/2003 9/1/2002 7/1/2003    
4. Construction 10/1/2002 8/1/2003 6/1/2003 4/9/2004    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue
4/22/2004Project completed 4/9/04.

2. Schedule/Timing Issues     

 

Date

Issue
4/22/2004Contractor has completed all construction and punch list items. Project is considered closed.

3. Fiscal/Resource Issues     

 

Date

Issue
3/28/2003Funding provided in the CIP Capital Maintenance Program.

4. Impact on Other Projects     

 

Date

Issue