Project Detail
Project Main Menu

Project Overview
Project Name: ES: Anderson Road / Watershed: Quantico/Little Creek
Project Type: Drainage Improvement Project
Project Description: A community along Anderson Road is experiencing flooding and erosion problems. Public Works will investigate, study, design and construct a storm drainage system to alleviate the problem. (Note: Revised End Date to be determined.)
Project Manager: Khalid Quraishi     send an email
Alternate Manager: Mukesh Patel     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Potomac
Original Budget: $50,000.00

Revised Budget:

$120,000.00
Original Start Date: 9/1/2000

Revised Start Date:

Original End Date: 3/31/2002

Revised End Date:

1/30/2004
Last Updated On: 8/2/2004 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Stormwater Management Fund/Drainage Fund

$50,000.00 ---
       
Total Amount: $50,000.00 $50,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Phase I: Right of Entry (From South Hampton Apartments to 4114 Anderson Road) (Note: Construction will be completed after Phase III) 10/1/2000 3/1/2002    
2. Phase I: Field Survey & Property acquisition (From South Hampton Apartments to 4114 Anderson Road) 12/1/2000 8/1/2001    
3. Phase I: Design (From South Hampton Apartments to 4114 Anderson Road) 6/1/2001 8/1/2001    
4. Phase I: Construction (From South Hampton Apartments to 4114 Anderson Road) NOTE: Start date will be determined after completion of Phase III. 10/15/2002 2/28/2003 1/30/2004    
5. Phase II: Right of Entry (From 4114 Anderson to 4107 Anderson Road) 10/1/2000 11/1/2000    
6. Phase II: Design (From 4114 Anderson to 4107 Anderson Road) 11/1/2000 12/1/2000    
7. Phase II: Construction (From 4114 Anderson to 4107 Anderson Road) 12/1/2000 1/1/2001    
8. Phase III: Right of Entry (From 4107 Anderson Road to 4204 Inn Street) 1/1/2001 5/1/2001    
9. Phase III: Field Survey (From 4107 Anderson Road to 4204 Inn Street) 5/1/2001 8/1/2001    
10. Phase III: Design (From 4107 Anderson Road to 4204 Inn Street) 8/1/2001 5/1/2003 12/1/2001 9/30/2003    
11. Phase III: Construction (From 4107 Anderson Road to 4204 Inn Street) NOTE: Construction start and completion date to be determined. 10/15/2002 2/28/2003    
12. Phase IV: Right of Entry (SWM Improvement at East Gate Apartments) 9/1/2000 10/1/2000    
13. Phase IV: Field Survey (SWM Improvement at East Gate Apartments) 10/1/2000 11/1/2000    
14. Phase IV: Design/Retrofit by the developer (SWM Improvement at East Gate Apartments) NOTE: Original End Date to be determined. 11/1/2001 3/31/2002    
15. Phase IV: Construction (SWM Improvement at East Gate Apartments) NOTE: Original Start Date and End Date to be determined. 11/1/2002 3/31/2003    
16. Phase V: Meeting with VDOT (Improvement of roadside ditch and driveway culverts by VDOT) 11/1/2000 2/1/2001    
17. Phase V: VDOT Study and Report (Improvement of roadside ditch and driveway culverts by VDOT) 12/1/2000 2/1/2001    
18. Phase V: Design upgrade negotiation with VDOT (Improvement of roadside ditch and driveway culverts by VDOT) 6/1/2002 6/30/2002    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue