Project Detail
Project Main Menu

Project Overview
Project Name: PA: Valley View Park
Project Type: New Construction
Project Description: Design and construction of a Sports Complex on the Valley View Park Property, including 5 lighted fields, two-story building, scorekeepers, 6 soccer fields, comfort station/concession building.
Project Manager: John Lyons     send an email
Alternate Manager:     
Agency Name: Park Authority QPR?: Yes
Magisterial District: Brentsville
Original Budget: $3,000,000.00

Revised Budget:

$5,419,000.00
Original Start Date: 10/1/2000

Revised Start Date:

10/1/2000
Original End Date: 10/1/2002

Revised End Date:

5/21/2004
Last Updated On: 7/29/2004 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. 1998 General Obligation Bond

$3,000,000.00 $3,474,000.00 6/26/2002

2. CIP/CMP Project Dollars

$0.00 $545,000.00 6/26/2002

3. Debt

$0.00 $1,300,000.00 8/7/2001

4. Va. Outdoors Fund Grant

$0.00 $100,000.00 1/1/2001
       
Total Amount: $3,000,000.00 $5,419,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Design 10/1/2000 6/1/2002  
2. Construction 8/7/2001 4/1/2003 5/21/2004 John Lyons  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue