Project Name: NS: Cardinal Drive Crape Myrtles and Flower Beds
Project Type: Flower beds in the medians from Donald Curtis Drive to Waterway Drive
Project Description: Crape Myrtles, planted in the medians along Cardinal Drive from Donald Curtis Drive to Eastlawn Avenue.
Project Manager: Ed W. Wheeling     send an email
Alternate Manager: Michelle M. Morris     
Agency Name: Neighborhood Services QPR?: Yes
Magisterial District: Potomac, Neabsco
Original Budget: $40,000.00

Revised Budget:

$50,000.00
Original Start Date: 4/1/2007

Revised Start Date:

10/23/2008
Original End Date: 5/1/2007

Revised End Date:

12/1/2008
Last Updated On: 4/20/2009 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. General Fund-Landscape budgets) and Proffer Contributions.

$10,000.00 --- 10/23/2008

2. General Fund-Landscape budgets) and Proffer Contributions.

$40,000.00 $55,000.00 7/1/2007
       
Total Amount: $50,000.00 $65,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Waiting for estimate from Dumfries Nursery. 7/16/2007 7/31/2007 1  
2. VDOT Permit approved 4/15/2007 7/15/2007 1  
3. 50% of planting has been completed. 5/20/2007 10/31/2007 1  
4. VDOT halted project until further review of plans. 5/1/2007 12/1/2007 7/1/2007 1/11/2008 1  
5. Project continued 4/1/2007 1/19/2008 2/29/2008 2/28/2008 1  
6. Second phase on hold until October 2008. Second phase will now consist of low laying grasses, perinials or flower beds instead of Crape Myrtle trees. 4/1/2007 10/1/2008 2/29/2008 10/29/2008 1  
7. Waiting on funding for project. 10/1/2008 10/23/2008 10/23/2008 12/1/2008 1  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
10/23/2008The second phase of the project has been changed from Crape Myrtles to low laying beds consisting of ornamental grasses, various bushes and small shrubs under 3 ft. Planting is scheduled to beging in November 2008.
2/14/2008The first phase of the project has been completed. The second phase of the project will consist of Crape Myrtles being planted in the median from the I-95 overpass to Stockholm Way. Planting is scheduled for October 2008.
2/1/200840 Crape Myrtles were relocated (at Neighborhood Services's expense) from the medians located at Waterway Dr and Knickerbocker Dr. The trees were relocated in other medians along Cardinal Dr.
12/1/2007VDOT has stopped any further planting of trees until the landscaping site has been physically inspected.
10/31/200750% of planting has been completed in the Neabsco District section of the project. The Dumfries section of the project is scheduled to begin in October 2008.
8/1/2007Planting of trees in medians will wait until ideal season October 2007. This gives the trees the best chance of survival.
6/1/2007Supervisor Caddigan and Supervisor Jenkins have been notified by way of email by Michelle Casciato as to the planting time line.