Project Name: PA: Catharpin Recreational Park formerly known as Sudley Park Sports Fields
Project Type: PROFFER
Project Description: Construction OF 5 diamond sports fields (lighted), 4 soccer fields (lighted), 2 football fields (lighted), travelways, parking and support structures.
Project Manager: John Lyons     send an email
Alternate Manager: Debbie Andrew     
Agency Name: PWCPA QPR?: Yes
Magisterial District: Gainesville
Original Budget: $2,500,000.00

Revised Budget:

$2,500,000.00
Original Start Date: 3/4/2002

Revised Start Date:

6/1/2008
Original End Date: 5/31/2007

Revised End Date:

12/31/2009
Last Updated On: 2/17/2010 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. 1998 Bond and Dominion Valley proffers (dollars and services)

$2,500,000.00 ---
       
Total Amount: $2,500,000.00 $2,500,000.00


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue
11/12/2008The opening of the diamond fields has been complete and pending the installation of the needed utilities for lights and irrigation, the project completion remains somewhat open ended as it pertains to the back section and lights for the fields, roadways and parking lots.

2. Schedule/Timing Issues     

 

Date

Issue
11/12/2008
11/12/2008Toll Brothers proffer work scheduled to be completed in 90-120 days. The five diamond fields have been completed and a punch list remains to be completed by Toll. The diamond fields are currently in play (there are no lights or infrastructure in place - Appeal on Planning Commission's decision to not permit lights to BOCS slated in November or December

3. Fiscal/Resource Issues     

 

Date

Issue
11/12/2008There remains approximately 1.6 million dollars in proffer dollards to be used for Silver Lake, Long Park and Catharpin Recreational Park. These funds along with the recreational trails grant funds from VDOT will aid in completing a large portion of the remaining infrastructure items which will support the irrigation system that is installed awaiting a final connection to the irrigation pond/well system as well as the much needed field lights.

4. Impact on Other Projects     

 

Date

Issue