Project Detail
Project Main Menu

Project Overview
Project Name: TD: Fuller Heights Road
Project Type: Revenue Sharing - Sidewalk Construction
Project Description: Provide curb, gutter and a sidewalk along the Southeast bound lane of Fuller Heights Road (Route 619) from Old Triangle Road (Route 1108) to St. Francis of Assissi Church.
Project Manager: Thomas J. Blaser     send an email
Alternate Manager: Kafayat U. Rahmani     
Agency Name: Transportation Division of Public Works QPR?: Yes
Magisterial District: Potomac
Original Budget: $316,915.00

Revised Budget:

$487,870.00
Original Start Date: 7/1/1999

Revised Start Date:

Original End Date: 12/31/2002

Revised End Date:

7/31/2004
Last Updated On: 8/30/2004 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. FY99-03 Revenue Sharing Funds - State Allocation

$158,693.00 $243,935.00 7/1/1999

2. FY99-03 Revenue Sharing Funds - County Allocation

$158,222.00 $243,935.00 7/1/1999
       
Total Amount: $316,915.00 $487,870.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right-of-way Research 9/1/2001 10/31/2001    
2. Engineering Survey 11/1/2001 1/31/2002    
3. Engineering Design 1/1/2002 2/28/2002 3/31/2002    
4. VDOT Review 2/1/2002 4/8/2002 3/31/2002 12/31/2002    
5. Addressing VDOT Comments 4/1/2002 1/1/2003 4/30/2002 4/30/2003    
6. VDOT Approval 5/1/2002 5/1/2003 5/31/2002 5/31/2003    
7. Right-of-way/Easements Acquisition 6/1/2002 6/1/2003 7/31/2002 7/31/2003    
8. Relocation of Utilities 8/1/2002 8/1/2003 9/30/2002 5/31/2004    
9. Construction 10/1/2002 10/1/2003 12/31/2002 7/31/2004    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue