Project Detail
Project Main Menu

Project Overview
Project Name: DOT: Glenkirk Road Improvements
Project Type: TRIP
Project Description: Glenkirk Road improvements to 3R standards north of Vint Hill Road (Route 215) to the south end of the Lake Manassas Dam.
Project Manager: Khattab O. Shammout     send an email
Alternate Manager: Kafayat U. Rahmani     
Agency Name: QPR?: Yes
Magisterial District: Brentsville
Original Budget: $3,241,518.00

Revised Budget:

$3,241,518.00
Original Start Date: 10/1/2007

Revised Start Date:

11/1/2008
Original End Date: 12/31/2009

Revised End Date:

8/31/2010
Last Updated On: 11/10/2011 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. State Secondary Road Funds

$1,900,000.00 --- 12/1/2009

2. FY2010 TRIP Funds

$217,143.00 --- 7/1/2009

3. Transfers for additional Work by County Construction Crew

$10,655.00 --- 3/16/2009

4. Transfers for R-O-W Acquisition

$400,000.00 --- 11/24/2008

5. Transfer from Burwell Rd. Pave-in-Place

$113,720.00 --- 7/31/2008

6. FY2009 TRIP Funds

$200,000.00 --- 7/1/2008

7. FY 2007 TRIP Funds

$400,000.00 --- 2/6/2007
       
Total Amount: $3,241,518.00 $3,241,518.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Engineering Design 10/1/2007 11/1/2008 4/30/2008 1/22/2009    
2. VDOT Approval 5/1/2008 2/1/2009 8/31/2008 7/31/2009    
3. Right-of-way/Easements Acquisition 9/1/2008 8/1/2009 12/31/2008 11/30/2009    
4. Environmental Certification 9/1/2008 8/1/2009 11/30/2008 11/30/2009    
5. Relocation of Utilities 9/1/2008 8/1/2009 12/31/2008 11/30/2009    
6. Bidding Process 11/1/2008 12/1/2009 1/31/2009 2/28/2010    
7. Construction 1/1/2009 3/1/2010 12/31/2009 8/31/2010    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue