Project Name: DOT: Benita Fitzgerald Drive Sidewalk
Project Type: TRIP
Project Description: Contruction of curb and gutter and a sidewalk on the west side of Benita Fitzgerald Drive between Dale Boulevard and Brazil Circle.
Project Manager: Khattab O. Shammout     send an email
Alternate Manager: Kafayat U. Rahmani     
Agency Name: QPR?: Yes
Magisterial District: Neabsco
Original Budget: $698,000.00

Revised Budget:

$698,000.00
Original Start Date: 10/1/2007

Revised Start Date:

Original End Date: 6/30/2009

Revised End Date:

6/30/2009
Last Updated On: 2/1/2010 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. FY 2009 TRIP Funds

$200,000.00 --- 11/12/2008

2. FY 2008 TRIP funds

$400,000.00 --- 12/18/2007

3. Transfer from OCA 400194

$10,000.00 --- 10/31/2007

4. FY 2007 TRIP Funds

$88,000.00 --- 2/6/2007
       
Total Amount: $698,000.00 $698,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Engineering Design 10/1/2007 7/31/2008    
2. VDOT Approval 8/1/2008 11/30/2008 10/17/2008    
3. Right-of-way/Easements Acquisition 10/1/2008 11/1/2008 12/31/2008    
4. Relocation of Utilities 10/1/2008 11/1/2008 12/31/2008    
5. Construction 1/1/2009 12/1/2008 6/30/2009    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue