Project Name: ES: 4391 Evansdale Road/Neabsco Creek
Project Type: Drainage Improvement Project
Project Description: (Project Code Number: 5725) Storm water runoff is causing standing water, sogginess, and flooding in the back yard of the property. Public Works will design and construct a drainage system to alleviate the problem.
Project Manager: Khalid Quraishi     send an email
Alternate Manager: Mukesh B. Patel     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Neabsco
Original Budget: $20,000.00

Revised Budget:

$20,000.00
Original Start Date: 6/5/2008

Revised Start Date:

Original End Date: 12/31/2008

Revised End Date:

Last Updated On: 4/20/2009 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. CIP

$20,000.00 ---
       
Total Amount: $20,000.00 $20,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right of Entry Agreement 6/5/2008 8/29/2008    
2. Meeting with the Property Owner, Site Visit & Develop Scope of Work 8/29/2008 9/19/2008    
3. Design of Drainage Improvement 9/19/2008 10/31/2008    
4. Design Approval by the Property Owner 10/31/2008 11/21/2008    
5. Develop Cost Estimate & Issue Task Order - contingent upon availability of funds 11/21/2008 12/12/2008    
6. Construction 12/12/2008 12/31/2008    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue