Project Detail
Project Main Menu

Project Overview
Project Name: DOT: Purcell Road Widening (Route 234 to west of Purcell Branch Crossing)
Project Type:
Project Description: Widening and realignment of Purcell Road to a four-lane divided roadway from intersection with Route 234 to west of Purcell Branch Crossing. Total distance of approx. 3,000 feet.
Project Manager: Thomas J. Blaser     send an email
Alternate Manager: Khattab O. Shammout     
Agency Name: Transportation QPR?: Yes
Magisterial District: Coles
Original Budget: $4,806,419.45

Revised Budget:

$4,806,419.45
Original Start Date: 1/1/2009

Revised Start Date:

5/1/2011
Original End Date: 8/31/2010

Revised End Date:

3/31/2013
Last Updated On: 9/24/2013 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Regional Surface Transportation Program (RSTP)

$2,189,151.00 --- 10/6/2009

2. Regional Surface Transportation Program (RSTP)

$2,000,000.00 --- 7/1/2009

3. Proffer Funding

$617,268.45 --- 7/1/2009
       
Total Amount: $4,806,419.45 $4,806,419.45



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Advertise RFP 1/1/2009 2/1/2009    
2. Final Plan Submission 8/1/2010 3/17/2011 8/31/2010 12/31/2011    
3. Design 5/1/2011 11/30/2011    
4. R-O-W & Utility Relocation 12/1/2011 2/28/2012    
5. Construction 3/1/2012 3/31/2013    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue