Project Name: ES: 14815 - 14821 Downey Court/Watershed: Neabsco Creek
Project Type: Drainage Improvement Project
Project Description: (Dale City, Project Code Number: 5559) Storm water runoff is causing standing water, sogginess, and flooding in the back yard of the property. Public Works will design and construct a drainage system to alleviate the problem.
Project Manager: Khalid Quraishi     send an email
Alternate Manager: Vakil A. Khan     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Neabsco
Original Budget: $40,000.00

Revised Budget:

$40,000.00
Original Start Date: 5/21/2008

Revised Start Date:

Original End Date: 6/30/2009

Revised End Date:

9/30/2010
Last Updated On: 3/10/2011 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. CIP

$40,000.00 ---
       
Total Amount: $40,000.00 $40,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right of entry agreements; Project qualification worksheet for public funding 5/21/2008 9/12/2008    
2. Selection of A/E vendor; Field survey; Preparation of easement plat 9/12/2008 11/28/2008    
3. Board resolution for accepting easement; Deed preparation by CAO 11/28/2008 2/27/2009    
4. Property owners notorized signatures on plat and deed 2/27/2009 3/31/2009 5/28/2010    
5. Design of storm drain system 3/31/2009 5/28/2010 4/30/2009 6/30/2010    
6. Material purchase; Installation of pipe and structures as per design 4/30/2009 6/30/2010 6/30/2009 9/30/2010    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue