Project Name: NS: Occoquan Commuter Lot Landscaping
Project Type: Landscaping, Beautification
Project Description: Trees, shrubs and flowers being planted in designated areas within the Occoquan commuter lot.
Project Manager: Ed W. Wheeling     send an email
Alternate Manager: Michelle M. Morris     
Agency Name: Neighborhood Services QPR?: Yes
Magisterial District: Occoquan
Original Budget: $5,000.00

Revised Budget:

$5,000.00
Original Start Date: 2/3/2009

Revised Start Date:

3/19/2009
Original End Date: 3/3/2009

Revised End Date:

11/15/2009
Last Updated On: 4/19/2010 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. (General Fund-Landscaping budgets)and Proffer Contributions. Plantings installed by inhouse staff.

$5,000.00 --- 2/3/2009
       
Total Amount: $5,000.00 $5,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. All plantings are being donated by Lake Ridge Nursery, so coordination for delivery is crutial to plantiing. 2/3/2009 3/3/2009 1  
2. Original plantings have been substituted for different species of plantings. Plans have been revised and submitted to VDOT for approval. 2/5/2009 2/25/2009 1  
3. All donated plantings for project were not in the regular inventory and had to be transferred. Ideal planting season has passed and project will continue in Oct 09. 3/3/2009 10/1/2009 5/3/2009 11/15/2009 1  
4. Landscaping project has continued as planned. All initial project plantings are not on hand at nursery. Substitutions will be made to complete project on-time. 3/1/2009 11/1/2009 4/1/2009 11/15/2009 1  
5. The porject was completed by the litter crew on November 15, 2009. 3/19/2009 11/15/2009  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
11/15/2009I have received all donated plantings from Lake Ridge Nursery. The project was completed by the litter crew on November 15, 2009.
8/21/2009Due to weather conditions and plant availability the project completion date has been moved back until November 2009.
3/3/2009Revised plans have been approved by VDOT.
2/5/2009Plans have been revised to show the substitution of the original plantings, because several species of trees would have been too large for planting area. Revised plans have been submitted to VDOT and are awaiting approval.

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue