Project Detail
Project Main Menu

Project Overview
Project Name: ES: 15439-15443 Marsh Overlook Drive/Watershed: Neabsco Creek
Project Type: Drainage Improvement Project
Project Description: (Woodbridge, Project Code Number: 5732) Storm water runoff is causing standing water, sogginess, and flooding in the back yard of the three properties. Public Works will design and construct a drainage system to alleviate the problem.
Project Manager: Khalid Quraishi     send an email
Alternate Manager: Vakil A. Khan     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Woodbridge
Original Budget: $40,000.00

Revised Budget:

$40,000.00
Original Start Date: 2/18/2009

Revised Start Date:

Original End Date: 12/31/2009

Revised End Date:

6/30/2010
Last Updated On: 1/13/2011 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. CIP

$40,000.00 ---
       
Total Amount: $40,000.00 $40,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right of entry agreements; Project qualification worksheet for public funding 2/18/2009 4/12/2009    
2. Selection of A/E vendor; Field survey; Preparation of easement plat 4/12/2009 6/30/2009 1/31/2010    
3. Board resolution for accepting easement; Deed preparation by CAO 6/30/2009 1/31/2010 9/30/2009 3/31/2010    
4. Design of storm drain system 9/30/2009 3/31/2010 10/30/2009 4/30/2010    
5. Material purchase 10/30/2009 4/30/2010 11/30/2009 5/31/2010    
6. Installation of pipe and structures as per design 11/30/2009 5/31/2010 12/31/2009 6/30/2010    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue